What I Learned Buying Solar, Storage and EV Charging for a UK Commercial Site
-
Start here: the parts that cost us money weren't the inverters
-
Who I am, and why this is worth reading
-
The four things that actually mattered
-
1. SMA solar inverters and the SMA DC disconnect: buy them as a matched pair
-
2. Battery storage installation in Westhoughton: the planning file outlasted the battery
-
3. Victron 100/50 solar controller: brilliant for the gatehouse, wrong for the main array
-
4. How to set up a commercial EV charging station: the software is the hard part
-
1. SMA solar inverters and the SMA DC disconnect: buy them as a matched pair
-
What I'd do differently next time
-
Where this advice doesn't apply
Start here: the parts that cost us money weren't the inverters
Our 2024 site upgrade turned out fine in the end, but the budget didn't go where I expected. The cheapest line on the quote — the DC disconnect — caused the most expensive delay of the whole project. The SMA inverters arrived on time, the panels were as ordered, and the battery was fine. What broke the schedule was a disconnect that didn't match the inverter's spec sheet, and a grid connection pack that wasn't ready when the installer needed it.
If you're a procurement person and someone in your company just handed you a solar-plus-storage-plus-EV-charging project, do this first: pin down the disconnects, the DNO paperwork, and the charge point software. Everything else is easier.
Who I am, and why this is worth reading
I'm the office administrator for a roughly 60-person engineering firm in the North West of England. I manage facilities spend — around £280,000 annually across a dozen suppliers — and I report jointly to operations and finance. In late 2023 I was told to coordinate a car park upgrade: 40 bays covered with solar canopies, a small commercial battery, and six dual-port EV chargers.
I'm not an electrician and I don't pretend to be. But I sign the contracts, I approve the invoices, and I'm the one who has to explain to the FD why a number on line 47 is suddenly £3,900 higher than expected. That's the seat this article comes from.
The four things that actually mattered
1. SMA solar inverters and the SMA DC disconnect: buy them as a matched pair
We specified three SMA inverters based on their reputation for reliability and their monitoring portal, which our maintenance contractor wanted. Good decision — no regrets there. The mistake was allowing the electrical subcontractor to source "an equivalent" DC disconnect from a wholesaler to save roughly £180 per unit.
"Equivalent" turned out to mean three different things on three different pages. The first batch didn't have the interrupting rating listed in the SMA manual for our array configuration. The second batch was correct but backordered four weeks. We ended up re-sourcing and paying £1,150 in expedited freight to hit the original energisation date.
Lesson: if the inverter datasheet names a disconnect specification, treat that as a requirement, not a suggestion. Write it into the purchase order as a line-item spec, and don't accept substitutions without a written engineer sign-off.
2. Battery storage installation in Westhoughton: the planning file outlasted the battery
One of our satellite sites is out near Westhoughton, and that's where we put the smaller of the two storage units. I naively assumed the battery would be the tricky part. It was the part everyone already knew how to do.
What nearly sank us was the paperwork. A grid-tied battery above 3.68 kW needs the DNO notified, and depending on the figure it can tip from G98 into G99 territory. Our first application was bounced because the installer's single-line diagram showed the storage on the wrong side of the metering. Two more rounds of correspondence later, we were six weeks behind — while the battery sat wrapped in a van bay at the supplier, accruing storage fees.
If I did it again, I'd add a line to the contract: installer to provide a DNO-ready application pack before the equipment is delivered. It's not glamorous, and no one will thank you for it, but it saves a month.
3. Victron 100/50 solar controller: brilliant for the gatehouse, wrong for the main array
The Victron SmartSolar MPPT 100/50 was recommended to me by two different people, and they weren't wrong — for the right job. It's rated for 100 V PV input and 50 A output, it's genuinely well-built, and the Bluetooth app is the easiest of any controller I've touched.
Where I almost went wrong was thinking I could use it as the controller for the whole canopy array. The 50 A limit and 100 V ceiling would have made that a non-starter once I actually did the string maths. We ended up using the Victron for the small off-grid circuit that runs the gatehouse lights and the CCTV mast. In that role it's been flawless for over a year.
That's a general pattern I'd flag: don't let a good product's reputation push it into a role it wasn't sized for. Match the controller to the array, not to the review score.
4. How to set up a commercial EV charging station: the software is the hard part
This is the one I'd warn any admin buyer about loudest. Six dual-port chargers is not a big install. Physically it went in over four days. But the part that ate months was choosing and commissioning the back-end — the charge point management system that handles authentication, pricing, and the driver app.
Two things I now treat as non-negotiable:
- OCPP 1.6J compliance on every unit. Open Charge Point Protocol is what lets you change software vendors later without replacing hardware. Skip it and you're locked in.
- A written list of software features that must be live on day one. Not "roadmap", not "coming soon". Live, tested, on our site, with our staff using it.
The first supplier we trialled had lovely hardware and a back-end that couldn't do variable tariffs without a paid upgrade we hadn't been shown. We walked away — politely, after month three — and started again with a smaller vendor who was honest about what was ready and what wasn't. That reset cost us nine weeks, but it saved us a five-year contract we'd have hated.
What I'd do differently next time
Three concrete changes to the procurement pack, not the technical spec:
- Any component named in an inverter manual becomes a line item with a spec, not a "suitable equivalent" note.
- DNO and planning document deliverables go on a milestone schedule with dates, tied to payment stages.
- Software acceptance testing gets its own sign-off gate, separate from the physical install. The hardware can be perfect and the project can still fail acceptance.
Where this advice doesn't apply
To be fair, if your project is a single domestic install or a straightforward sub-4 kW retrofit, most of what I've written here is overkill. A good MCS-certified installer will handle the DNO side and the disconnect sourcing without you needing to police every line. The effort-per-pound calculation only starts to pay off once you're above roughly 20 kW, or once you're integrating storage and EV charging on the same site — because that's when the interfaces between systems start failing in ways no single vendor owns.
And one honest caveat: we still had a two-week slip on the final commissioning, entirely because of a landscaping clash I approved the week before. No amount of procurement rigour fixes a project manager who lets a contractor dig a trench in the wrong place. I'm still slightly embarrassed about that one.